Located approximately 120 km off the Norfolk coast, Ørsted’s Hornsea 3 is set to become the world’s largest single offshore wind farm upon completion in 2027. The £8.5 billion development will have a generating capacity of 2.9 GW, enough to power more than 3.3 million UK homes. Electricity generated offshore will be converted to high-voltage direct current (HVDC) for transmission through subsea and onshore export cables to an onshore converter station, where it will be converted back to alternating current for connection to National Grid’s 400 kV Norwich Main Substation.

As part of this major infrastructure programme, Hitachi Energy is responsible for the design, installation and commissioning of four 400 kV air-insulated switchgear (AIS) feeder circuits at Norwich Main. Working with Hitachi, Whitfield Consulting Services (WCS) is delivering civil engineering design for the substation extension, including high-voltage plant foundations, Portable Relay Room (PRR) bases, SF6 access paths and hardstandings, and cable containment layouts incorporating precast trenches and ducting routes.

In this case study, Victor Lupusor, Principal Structural Engineer at WCS, explains how the team coordinated complex design interfaces, optimised foundation designs to reduce embodied carbon, resolved construction-stage challenges and provided technical support and temporary works coordination throughout the project.

Coordinating civil design across multiple project interfaces

WCS worked closely with Hitachi Energy and other project stakeholders to coordinate civil and electrical design interfaces, identify potential clashes and reduce the risk of construction delays.

“We had multiple principal contractors working on site, each with their own designs. It was about sharing information, making sure everything aligned and avoiding clashes and delays,” explains Victor.

Key areas of coordination included aligning foundations and cable containment with electrical layouts and earthing systems and adapting designs to developing site requirements.

Within its design package, WCS used Autodesk Construction Cloud (ACC) as a common data environment, supported by 3D BIM modelling and regular model exchanges. As other contractors followed separate design protocols, regular meetings, information exchanges and site visits helped maintain coordination across the wider project.

Civil design solutions and sustainability

Across the substation extension, WCS’s engineering decisions contributed to an embodied carbon reduction of up to 25%.

WCS developed foundation and cable containment solutions to support the installation of the new high-voltage equipment. Where appropriate, common foundation sizes were grouped together for structures with comparable loading conditions to simplify and standardise the construction process. Standard precast cable troughs were incorporated wherever suitable for the same reasons.

A significant achievement involved optimising the PRR foundations. The original concept proposed a ground-bearing reinforced concrete slab covering the building’s entire footprint, consistent with previous installations.

Rather than replicating the established approach, WCS investigated the PRR’s structural arrangement and load paths to determine where support was required. This demonstrated that a perimeter strip foundation could provide the necessary support without requiring a slab across the entire footprint, maintaining structural performance while reducing the concrete required for the PRR foundations by more than 50%.

By challenging the original design assumptions, WCS identified an opportunity to improve material efficiency and reduce the associated embodied carbon without compromising the required structural performance.

Construction support: Resolving high-voltage cable clashes

WCS provided technical support during construction, working with the site team to resolve design coordination issues and develop practical engineering solutions.

One example involved the Cable Sealing End (CSE) foundations. During construction, the electrical design team identified that the high-voltage cable arrangement required on site differed from the original model information used to design the foundations. The revised arrangement introduced a clash with the concrete foundations, and WCS was asked to develop a remedial solution.

With some foundations already cast, WCS proposed localised notching of the reinforced concrete to provide the necessary cable clearance. For foundations yet to be constructed, the team adjusted the designs to accommodate the revised cable arrangement.

These solutions allowed the existing foundations to be retained, avoiding unnecessary demolition and supporting continued construction progress.

Responding to construction challenges

WCS also provided additional engineering support to address unforeseen site conditions.

Where existing drainage services, which had not been fully identified in the available records, were exposed during construction, the team developed protection measures to safeguard the infrastructure from damage during the works.

In another instance, testing identified that the concrete strength of a structure was below the original design specification. WCS undertook a structural assessment confirming that the achieved strength remained adequate for the required structural performance, avoiding unnecessary reconstruction.

These interventions illustrate how WCS’s continued involvement and responsiveness beyond the original detailed design remit enabled technical issues to be assessed and resolved through targeted engineering solutions, minimising unnecessary remedial works.

Temporary works coordination and construction oversight

Alongside permanent works design and construction support, WCS provided Temporary Works Coordinator (TWC) services, with Victor overseeing procedures in accordance with BS 5975.

“While WCS didn’t design the temporary works, as TWC, my role was to manage and coordinate them, making sure everything was registered, the risks were assessed, and the required documentation was in place,” explains Victor.

Victor undertook site visits and carried out periodic audits of the civil contractor’s temporary works documentation. As part of the role he maintained regular communication with the Temporary Works Supervisor and the contractor’s temporary works team between visits.

This continued oversight and continuity helped maintain visibility of temporary works risks, ensure the appropriate procedures were followed and manage interfaces with the permanent works as construction progressed.

For more information about WCS’s temporary works capabilities, including the TWC role and its responsibilities, read our article: Spotlight on the role of the Temporary Works Coordinator.

The WCS approach: From design to commissioning

WCS’s involvement at Norwich Main extended from early design through construction and into commissioning, providing continuity between design development and implementation on site.

Working closely with Hitachi Energy and the wider project team, WCS delivered coordinated civil engineering designs that supported the integration of new high-voltage infrastructure, while optimising foundation solutions to reduce material use and embodied carbon.

Beyond design, the team’s responsive construction support helped resolve unforeseen technical challenges, avoid unnecessary remedial works and maintain construction progress. Combined with its Temporary Works Coordinator role, this provided valuable engineering expertise and oversight throughout the construction phase.

Building on its established relationship with Hitachi Energy, the project demonstrates WCS’s ability to combine sustainable design, multidisciplinary coordination and practical construction-stage support to help deliver complex Power & Energy infrastructure.